Wednesday 1 July 2015

About piles

End Bearing Piles ::-

1:-In end bearing piles, the bottom end of the pile rests on a layer of especially strong soil or rock.
2:- The load of the building is transferred through the pile onto the strong layer.
3:-In a sense, this pile acts like a column.
4:-The key principle is that the bottom end rests on the surface which is the intersection of a weak and strong layer. The load therefore bypasses the weak layer and is safely transferred to the strong layer.


Friction Piles ::-

1:-Friction piles work on a different principle.
2:- The pile transfers the load of the building to the soil across the full height of the pile, by friction.
3:-In other words, the entire surface of the pile, which is cylindrical in shape, works to transfer the forces to the soil.



NOTE: In practice, however, each pile resists load by a combination of end bearing and friction

Tuesday 30 June 2015

POINTS TO REMEMBER FOR CIVIL SITE ENGINEERS

Following are few general points to remember for civil site engineers to make the construction work easier while maintaining quality of construction.
  • Lapping is not allowed for the bars having diameters more than 36 mm.
  • Chair spacing maximum spacing is 1.00 m (or) 1 No per 1m2.
  • For dowels rod minimum of 12 mm diameter should be used.
  • Chairs minimum of 12 mm diameter bars to be used.
  • Longitudinal reinforcement not less than 0.8% and more than 6% of gross C/S.
  • Minimum bars for square column is 4 No’s and 6 No’s for circular column.
  • Main bars in the slabs shall not be less than 8 mm (HYSD) or 10 mm (Plain bars) and the distributors not less than 8 mm and not more than 1/8 of slab thickness.
  • Minimum thickness of slab is 125 mm.
  • Dimension tolerance for cubes + 2 mm.
  • Free fall of concrete is allowed maximum to 1.50m.
  • Lap slices not be used for bar larger than 36 mm.
  • Water absorption of bricks should not be more than 15 %.
  • PH value of the water should not be less than 6.
  • Compressive strength of Bricks is 3.5 N / mm2.
  • In steel reinforcement binding wire required is 8 kg per MT.
  • In soil filling as per IS code, 3 samples should be taken for core cutting test for every 100m2.

Density of Materials:

Material
Density
Bricks
1600 – 1920 kg/m3
Concrete block
1920 kg/ m3
Reinforced concrete
2310 – 2700 kg/ m3

Curing time of RCC Members for different types of cement:

Super Sulphate cement: 7 days
Ordinary Portland cement OPC: 10 days
Minerals & Admixture added cement: 14 days

De-Shuttering time of different RCC Members

RCC Member
De-shuttering time
For columns, walls, vertical form works
16-24 hrs.
Soffit formwork to slabs
3 days (props to be refixed after removal)
Soffit to beams props
7 days (props to refixed after removal)
Beams spanning upto 4.5m
7 days
Beams spanning over 4.5m
14 days
Arches spanning up to 6m
14 days
Arches spanning over 6m
21 days

Cube samples required for different quantity of concrete:

Quantity of Concrete
No. of cubes required
1 – 5 m3
1 No’s
6 0 15 m3
2 No’s
16 – 30 m3
3 No’s
31 – 50 m3
4 No’s
Above 50 m3
4 + 1 No’s of addition of each 50 m3

Monday 25 May 2015

A Step-by-Step Guide to the Home Building Process

1. Prepare site and pour foundation: Often, site preparation and foundation work are performed by the same crew, but this may not be the case with a wooded lot. Using a backhoe and a bulldozer, the crew clears the site of rocks, debris and trees for the house and, if applicable, the septic system. The crew levels the site, puts up wooden forms to serve as a template for the foundation, and digs the holes and trenches. Footings (structures where the house interfaces with the earth that supports it) are installed. If your home is going to have a well, it will be dug at this point.
If the home has a full basement, the hole is dug, the footings are formed and poured, and the foundation walls are formed and poured. If it’s slab-on-grade, the footings are dug, formed and poured; the area between them is leveled and fitted with utility runs (e.g. plumbing drains and electrical chases); and the slab is poured.
Once concrete is poured into the holes and trenches, it will need time to cure. During this period, there will be no activity on the construction site.
After the concrete is cured, the crew applies a waterproofing membrane to the foundation walls; installs drains, sewer and water taps and any plumbing that needs to go into the first-floor slab or basement floor; and backfills excavated dirt into the hole around the foundation wall. 
INSPECTION #1: When the curing process is complete, a city inspector visits the site to make sure foundation components are up to code and installed properly. This inspection may be repeated depending on the type of foundation (slab, crawl space or basement). Your builder will then remove the forms and begin coordinating step 2, the framing phase.
2. Complete rough framing: The floor systems, walls and roof systems are completed (collectively known as the shell or skeleton of the house). Plywood or oriented strand board (OSB) sheathing is applied to the exterior walls and roof, and windows and exterior doors are installed. The sheathing is then covered with a protective barrier known as a house wrap; it prevents liquid water from infiltrating the structure, while allowing water vapor to escape. This reduces the likelihood of mold and wood rot.
3. Complete rough plumbing, electrical and HVAC: Once the shell is finished, siding and roofing can be installed. At the same time, the electrical and plumbing contractors start running pipes and wires through the interior walls, ceilings and floors. Sewer lines and vents, as well as water supply lines for each fixture, are installed. Bathtubs and one-piece shower/tub units are put in place at this point because there’s more room to maneuver large, heavy objects.
Ductwork is installed for the heating, ventilation and air-conditioning (HVAC) system, and possibly the furnace. HVAC vent pipes are installed through the roof, and insulation is installed in the floors, walls and ceilings.
After the roofing goes on, the house is considered “dried in.” The electrician then installs receptacles for outlets, lights and switches and runs wires from the breaker panel to each receptacle. Wiring for telephones, cable TV and music systems is included in this work.
Note that HVAC ducts and plumbing are usually installed before wiring, because it’s easier to run wires around pipes and ducts than vice versa.
INSPECTIONS 2, 3 and 4: Rough framing, plumbing and electrical and mechanical systems are inspected for compliance with building codes. Most likely these will be three different inspections. At the very least, the framing inspection will be conducted separately from the electrical/mechanical inspections.
At this stage, drywall (also known as plasterboard, wallboard or gypsum board) is delivered to the building site. Sheetrock®, a registered trademark of USG Corporation, is sometimes used as a generic term for drywall.
4. Install insulation: Insulation plays a key role in creating a more comfortable, consistent indoor climate while significantly improving a home’s energy efficiency. One of the most important qualities of insulation is its thermal performance or R-value, which indicates how well the material resists heat transfer. Most homes are insulated in all exterior walls, as well as the attic and any floors that are located above unfinished basements or crawl spaces.
The most common types of insulation used in new homes are fiberglass, cellulose and foam. Depending on the region and climate, your builder may also use mineral wool (otherwise known as rock wool or slag wool); concrete blocks; foam board or rigid foam; insulating concrete forms (ICFs); sprayed foam; and structural insulated panels (SIPs).
Blanket insulation, which comes in batts or rolls, is typical in new-home construction. So is loose-fill and blown-in insulation, which is made of fiberglass, cellulose or mineral-wool particles. Another insulation option, liquid foam, can be sprayed, foamed-in-place, injected or poured. While it costs more than traditional batt insulation, liquid foam has twice the R-value per inch and can fill the smallest cavities, creating an effective air barrier.
Fiberglass and mineral-wool batts and rolls are usually installed in side walls, attics, floors, crawl spaces, cathedral ceilings and basements. Manufacturers often attach a facing such as kraft paper or foil-kraft paper to act as a vapor barrier and/or air barrier. In areas where the insulation will be left exposed, such as basement walls, the batts sometimes have a special flame-resistant facing.
5. Complete drywall and interior textures; start exterior finishes: Drywall is hung and taped so the seams between the boards aren’t visible, and drywall texturing (if applicable) is completed. The primer coat of paint is also applied after taping is complete. Contractors begin installing exterior finishes such as brick, stucco, stone and siding.
6. Finish interior trim; install exterior driveways and walkways: Interior doors, baseboards, door casings, window sills, moldings, stair balusters and other decorative trim are installed, along with cabinets, vanities and fireplace mantels and surrounds. Walls get a finish coat of paint and are wallpapered where applicable.
Generally, exterior driveways, walkways and patios are formed at this stage. Many builders prefer to wait until the end of the project before pouring the driveway because heavy equipment (such as a drywall delivery truck) can damage concrete. But some builders pour the driveway as soon as the foundation is completed so that when homeowners visit the construction site, they won’t get their shoes muddy.
7. Install hard-surface flooring and countertops; complete exterior grading: Ceramic tile, vinyl and wood flooring are installed as well as countertops. Exterior finish grading is completed to ensure proper drainage away from the home and prepare the yard for landscaping.
8. Finish mechanical trims; install bathroom fixtures: Light fixtures, outlets and switches are installed and the electrical panel is completed. HVAC equipment is installed and registers completed. Sinks, toilets and faucets are put in place.
9. Install mirrors, shower doors and finish flooring; finish exterior landscaping:Mirrors, shower doors and carpeting are installed, and final cleanup takes place. Trees, shrubs and grass are planted and other exterior landscaping completed.
INSPECTION #5: A building-code official completes a final inspection and issues a certificate of occupancy (C.O.). If any defects are found during this inspection, a follow-up inspection may be scheduled to ensure that they’ve been corrected.
10. Final walkthrough: Your builder will walk you through your new home to acquaint you with its features and the operation of various systems and components, and explain your responsibilities for maintenance and upkeep as well as warranty coverage and procedures. This is often referred to as a pre-settlement walkthrough. It’s also an opportunity to spot items that need to be corrected or adjusted, so be attentive and observant. Examine the surfaces of countertops, fixtures, floors and walls for possible damage. Sometimes disputes arise because the homeowner discovers a gouge in a countertop after move-in, and there’s is no way to prove whether it was caused by the builder’s crew or the homeowner’s movers.
A Few Words about Inspections: Your new home will be inspected periodically during the course of construction. In addition to mandated inspections for code compliance, your builder may conduct quality checks at critical points in the process. (In the story above, we point out when these inspections typically take place.) The idea is to catch as many potential problems as possible before construction is finished, though some issues may not surface until you’ve lived in the home for a period of time.
Talk to your builder early on about attending inspections, with or without your real-estate agent. Even if your presence is not required, it’s an opportunity to learn more about what’s behind the walls of your new home and how everything works. If you’re planning to hire your own inspector to do an additional review of the home, notify your builder prior to the start of construction.
For safety as well as logistical reasons, builders discourage customers from dropping in unannounced at the construction site. If you’d like to pay a visit, be sure to arrange it in advance. Chances are your builder will conduct regular walkthroughs to bring you up to speed on the progress of the work.
Working with the builder who'll construct your new home is the fifth of six steps to your new home. Here in our New Home Guide, you'll find helpful and inspiring articles, slideshows and videos that will make your new home journey easier and more rewarding.